Comparing the Costs of Cross Laminated Timber and Reinforced Concrete Structures

Readers will be interested in the findings of a recent study completed by Cary Kopczynski & Company, that compares the cost of the structural frame of a hypothetical 10-story residential building located in the Pacific Northwest using cross laminated timber (CLT) and cast-in-place reinforced concrete.

Based on a survey of contractors knowledgeable in CLT construction, the cost of the structural frame in the CLT option was estimated to be $48 to $56 per gross square foot excluding costs for acoustical dampening and fire protection. Acoustical and fire protection costs are expected to range from $2 to $6 per square foot.

The cost of the structural frame in the cast-in-place reinforced concrete option is estimated to range from $42 to $46 per gross square foot. Additional cost for acoustical dampening may be required, which is estimated to be in the range of $1 to $2 per square foot.

The results of the study suggest that the cost of the structural frame for the CLT option is about 16 to 29% greater than that of the cast-in-place reinforced concrete option.

The results from this study show that CLT structures cost significantly more than cast-in-place reinforced concrete structures. Square foot costs of some actual CLT projects are also greater than comparable reinforced concrete structures based on national average structure costs. It is expected that the costs would be even greater for CLT projects outside the Pacific Northwest where the majority of CLT production facilities are located.

 

The study noted also that the choice of structural material has limited impact on the total energy consumed over a building’s life, since the structure affects only Embodied Energy – the energy required to produce the building’s physical materials. Operational Energy – the energy required to heat, cool, light, and operate a building – is dominant, being upwards of 95% of the total energy consumed.

It was observed that for the ten-story building evaluated, the concrete option is less susceptible to floor vibration under dynamic loads, and to excessive lateral drift under wind and seismic loads unless concrete shear walls are substituted for CLT walls in the CLT Option. Concrete shear walls in the CLT Option would require measures to control differential axial shortening between the concrete and gravity load carrying vertical wood elements.

The authors of the original study caution readers to use judgement when drawing conclusions from the data presented in the report. This is especially true for cost and constructability, since the available CLT information is limited and costs vary widely from region to region.

The full study, “Cary Kopczynski & Company, 2018, Cross Laminated Timber Feasibility Study – A comparison between cross laminated timber and cast-in-place concrete framing for mid-rise urban buildings. Seattle, WA.” Is available here. A shorter summary of the report appears as a CRSI Technical Note, which is available here.  Graphics sourced from the above noted study.

 

Frank Came

Recent Posts

MIT-derived algorithm helps forecast the frequency of extreme weather

The new approach “nudges” existing climate simulations closer to future reality.

3 weeks ago

First Ever Federal Blueprint to Decarbonize America’s Buildings Sector

First Comprehensive Federal Strategy Outlines Pathways to Reduce Emissions 90% in Buildings Sector by 2050,…

4 weeks ago

Modular Construction Is an Uplifting Solution for Sustainable Projects

Technological advances and innovation make modular construction a great way to combat the delays of…

1 month ago

Thin, bacteria-coated fibers could lead to self-healing concrete that fills in its own crack

Some say there are two types of concrete – cracked and on the brink of…

1 month ago

NRMCA Concrete Carbon Calculator How to Reduce, Quantify, and Specify Carbon

This simole web-based tool empowering design and build teams to specify low-carbon concrete for various…

2 months ago

CALSTART and PNWER complete the design of Washington State’s zero-emission commercial vehicle incentive program

A major initiative has been launched to accelerate the adoption of medium- and heavy-duty zero-emission…

2 months ago